In a recent judgment dated 12 May 2023 in the case of Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC [2022] DIFC CA 106/2022, the DIFC Court of Appeal (“CA”) considered various topical issues in construction disputes in the Middle East.
Introduction
The facts underlying the dispute between the contractor (“MESC”) and the employer (“Panther”) in the Panther case are typical of construction projects in the GCC: in 2017 the parties signed a contract for the construction of a residential tower in Dubai based on the FIDIC Redbook 1999 as supplemented and amended by a set of particular conditions. The project was then delayed. The contractor (“MESC”) submitted various extension of time (“EOT”) claims which were rejected. MESC served a notice of slowdown of the works. The parties attempted to resolve their dispute amicably but to no avail. Panther then proceeded to liquidate the security guarantees and in late 2019 ultimately served a termination letter under Sub-Clause 15.2 (which provided that Panther was entitled to terminate the contract with immediate effect if, amongst other things the maximum amount of delay damages was exhausted, as they alleged it was). Shortly after, Panther appointed another contractor to complete the project.
At first instance, the DIFC Court found Panther responsible for most of the delay. However, the court also found that MESC had not complied with the notice requirements as regards to its EOT claims, which resulted in:
- MESC losing its right to an EOT and/or additional costs; and
- Panther being entitled to liquidated delay damages.