< Back to insights hub

Article

Vietnam issues Implementation Plan of Power Development Plan 824 April 2024

On 1 April 2024, the Vietnamese Prime Minister issued Decision No. 262/QD-TTg approving the plan for implementation of the National Power Development Master Plan for the period from 2021 to 2030, with a vision to 2050 (the “PDP8 Implementation Plan”). The PDP8 Implementation Plan provides guidelines to achieve relevant goals as set out in the National Power Development Master Plan, which was issued in May 2023. With specific contents regarding power generation and transmission projects, as well as relevant programmes to supplement policy and regulatory framework, the PDP8 Implementation Plan is considered a positive step towards resolving current barriers and expediting development of the power sector in Vietnam.

"The PDP8 Implementation Plan is considered a positive step towards resolving current barriers and expediting development of the power sector in Vietnam."

1.  Thermal power projects

As set out in the National Power Development Master Plan, the thermal power sources to be developed from 2021 to 2030 include domestic gas, LNG, and coal with a total capacity of 14,930 MW, 22,400 MW and 30,127 MW respectively.

The PDP8 Implementation Plan sets out in Table 1, 2, and 3 of Annex III details of domestic gas, LNG and coal power projects to be developed until 2030, including name, planned capacity, location, required year of operation and additional notes on the project status.

Among those listed, the following projects have been classified as projects of national importance, priority projects under Decision No. 270/QD-TTg dated 2 April 2024 of the Prime Minister:

ProjectCapacityProject status
Domestic gas-to-power project chains
Block B gas-to-power project chain:

• upstream gas field development project;
• midstream gas transportation project; and
• downstream gas-fueled power plants.
Capacity of four power plants (O Mon 1, 2, 3, and 4): 3,810 MWUnder development
Ca Voi Xanh gas-to-power project chain:

• upstream gas field development project; and
• downstream gas-fueled power plants.
Capacity of five power plants (Mien Trung 1 & 2, Dung Quat 1, 2 & 3): 3,750 MWUnder development
LNG-fuelled power plants (importing from regional terminal)
Quang Trach 2 power plant1,500 MWUnder development
Nhon Trach 3 & 4 power plant1,624 MWUnder construction
Long An 1 power plant1,500 MWPreparing feasibility study
LNG-to-power project chains (including terminal and power plant(s)
Son My projectTwo power plants with capacity of 2,250 MW per power plantPreparing feasibility study
Quang Ninh project1,500 MWPreparing feasibility study
Thai Binh project1,500 MWUnder development
Nghi Son/Quynh Lap project2 power plants with capacity of 1,500 MW per power plantNghi Son power plant: Selecting investor

Quynh Lap power plant: Under development
Hai Lang Phase 1 project1,500MWPreparing feasibility study
Ca Na project1,500 MWSelecting investor
Bac Lieu project3,200 MWPreparing feasibility study
Coal-fired power plants
Quang Trach 1 power plant1,403 MWUnder construction
Long Phu 1 power plant1,200 MWUnder construction

< Back to insights hub

"A key concern for investors in renewable power projects in general and onshore and nearshore wind power projects is upcoming tariff policy."

2.  Renewable power projects

The PDP8 Implementation Plan provides instruction for each type of renewable power projects, including wind, solar, hydro and other power sources. Notably, for wind and solar power projects, the PDP8 Implementation Plan has assigned relevant authorities to resolve regulatory challenges faced by investors, including:

2.1 Wind power projects for consumption within Vietnam

(i) Onshore and nearshore wind power projects

The PDP8 Implementation Plan provides in Table 9 of Annex III details of onshore and nearshore wind power projects to be developed until 2030, including name, planned capacity, location, required year of operation and additional notes on the project status with total capacity of 21,880 MW.

Given the expiration of feed-in-tariff policies, a key concern for investors in renewable power projects in general and onshore and nearshore wind power projects is upcoming tariff policy. The PDP8 Implementation Plan assigns the Ministry of Industry and Trade (“MOIT”) to organise and coordinate with relevant authorities in constructing and promulgating tariff range for different types of power projects. For wind power projects, Circular 15/2022/TT-BCT dated 3 October 2022 and Circular 19/2023/TT-BCT dated 1 November 2023 have provided clear regulatory framework for calculation of annual tariff range for wind power projects in the interim (i.e. projects that have signed PPA but did not meet COD before the required COD) which are not eligible for feed-in-tariff.

Besides tariff range, investors are also awaiting instructions on negotiation of power purchase agreement (“PPA”) and tariff. On 29 December 2023, the MOIT has published for consultation a draft circular which intends to regulate the method for calculation of tariff and negotiation of PPA for specific projects. The draft circular covers a broad range of projects, including thermal, renewable power projects and projects using new sources of energy such as hydrogen or ammonia. Accordingly, investors and utility offtaker Vietnam Electricity (“EVN”) will negotiate the project PPA and tariff, subject to the yearly tariff range approved by MOIT as analysed above.

(ii) Offshore wind power projects

The PDP8 Implementation Plan provides in Table 1 of Annex II the regional allocation of capacity of offshore wind power to be developed until 2030 with total capacity of 6,000 MW.

So far, due to an insufficient regulatory framework, there has not been any approval for development of offshore wind power projects in Vietnam. The PDP8 Implementation Plan assigns the Ministry of Planning and Investment (“MPI”) to research and propose to the competent authority to promulgate regulations on authority for approval of offshore wind power projects. Meanwhile, state-owned enterprises EVN and Vietnam Oil and Gas Group (“PVN”) have been assigned to research the capability and conditions for implementation of offshore wind power projects to be ready when obtaining permission for development from competent authority.

2.2 Solar power projects for consumption within Vietnam

(i) Concentrated solar power projects

Under the National Power Development Master Plan, the total capacity of concentrated solar power projects to be developed until 2030 is 10,236 MW. Projects that obtained approval for investment will be subject to different treatments depending on their status of investor selection, specifically:

  1. For projects that have been assigned to a specific investor, the competent authority will assign specific development progress targets to these projects taking into account relevant regulations, assurance of energy security, balance of sources and loads, grid infrastructure, economic efficiency, appropriate tariff and transmission costs. Under the PDP8 Implementation Plan, the MOIT is assigned to coordinate with provincial authorities to complete reviewing these projects and submit the list of projects to be developed by 2030 to the Prime Minister for approval before 30 April 2024.
    Similar to wind power projects as analysed in Section 2.1(i), these projects will be required to negotiate PPA and tariff with EVN, subject to the yearly tariff range approved by MOIT.
  2. For projects that have not been assigned to specific investor, such projects as listed in Annex IV of the National Power Development Master Plan will only be considered for development after 2030, unless the projects are implemented under a self-consumption model and comply with regulations on planning, land use and other matters.

(ii) Rooftop solar power projects

The PDP8 Implementation Plan provides in Table 6 of Annex II the provincial allocation of capacity of rooftop solar power projects to be developed until 2030 on self-consumption basis with total capacity of 2,600 MW.

"The PDP8 Implementation Plan provides for 5,000 MW to 10,000 MW of renewable power projects to export to other countries."

So far, MOIT has been coordinating with relevant authorities to prepare a governmental decree on the development of rooftop solar power projects on a self-consumption basis. The decree intends to clarify definitions relating to self-consumption rooftop solar power projects, limitation of development, requirements for registration and compliance with relevant laws (for both grid-connected and non-grid-connected projects).

2.3 Other renewable power projects for consumption within Vietnam

Besides wind and solar power projects, the PDP8 Implementation Plan provides details on projects of other renewable sources to be developed until 2030, including:

Types of renewable sourcesTotal capacity for developmentReferences on project details
Hydropower projects29,346 MWMid and large-scale projects: Table 6 of Annex III

Small-scale projects: Table 10 of Annex III
Hydro pump-storage projects2,400 MWTable 7 of Annex III
Co-firing projects, projects using residual heat, blast furnace gas, by-products of production line2,700 MWTable 5 of Annex III
Biomass projects1,088 MWTable 11 of Annex III
Waste-to-energy projects1,182 MWTable 12 of Annex III
Battery storage projects (integrated in other renewable projects)300 MWTable 8 of Annex III
2.4 Renewable power projects for export

The PDP8 Implementation Plan provides for 5,000 MW to 10,000 MW of renewable power projects (potentially in Vietnam’s central and southern regions) to export to other countries. The approval for these renewable power projects will be given in alignment with the approval for policy for power exportation and approval for related grid connection projects.

3.  Power transmission projects

The PDP8 Implementation Plan provides in Annex V the lists of important, priority grid projects, including projects to connect domestic sources and projects to import electricity from neighbouring countries (e.g. Laos and China). It also notes that the lists are subject to future updates upon approval of additional renewable power projects (e.g. concentrated solar power projects as analysed in Section 2.2(i).

Hanoi Legal Trainee Quynh Nguyen also contributed to this article.

< Back to insights hub